Cernavoda 3 and 4 decisions forthcoming
Friday, 29 June 2007
An earlier version of this story incorrectly stated that Cernavoda 2 would achieve commercial operation and full power in July. In fact it is planned to achieve 100% power in July, and commercial operation in September.
The Romanian nuclear industry expects Cernavoda 2 to begin commercial operation in September and government approval for the completion of units 3 and 4 within days.
Teodor Chirica, CEO of state generator Nuclearelectrica, said that Cernavoda 2 was in the final commissioning stage. After receiving permission from regulators, it had achieved 5% power and would progress to 100% in July and full commercial operation in September.
He also stated that before the end of June the Romanian government would approve the completion of units 3 and 4. Chirica was speaking at a London meeting, Nuclear New Build: The Role of the Private Sector, on 27 June.
The Cernavoda plant was originally intended to host five Canadian Candu pressurized heavy water reactors of 633 MWe each. Construction on units 2-5 has halted in 1991 in order to concentrate on unit 1, which entered commercial operation at the end of 1996. It now provides 10% of the country's electricity.
The government decided to resume work on unit 2 in 2000. After some upgrades during completion, unit 2 is rated at 655 MWe.
Negotiations to assemble a commercial consortium for the completion of units 3 and 4 are underway. It is expected that a project company would be formed and work begin in March 2008.
Chirica said the 64 month completion project would cost Eur2.2 billion ($3.0 billion), not including the cost of capital, but would result in two 720 MWe units with 30-40 year lives. He projected the cost of electricity generation by the units would be between Eur28.2-32.5 per MWh ($38.1-43.7).
The units would be constructed in parallel with a gap of "a couple of months" between each unit's start-up around 2014-5.
Further information
Nuclearelectrica
WNA's Nuclear Power in Romania information paper
WNN: Cernavoda 2 achieves initial criticality
CORRECTED The Romanian nuclear industry expects Cernavoda 2 to begin commercial operation in September and government approval for the completion of units 3 and 4 within days.
An earlier version of this story incorrectly stated that Cernavoda 2 would achieve commercial operation and full power in July. In fact it is planned to achieve 100% power in July, and commercial operation in September.
The Romanian nuclear industry expects Cernavoda 2 to begin commercial operation in September and government approval for the completion of units 3 and 4 within days.
Teodor Chirica, CEO of state generator Nuclearelectrica, said that Cernavoda 2 was in the final commissioning stage. After receiving permission from regulators, it had achieved 5% power and would progress to 100% in July and full commercial operation in September.
He also stated that before the end of June the Romanian government would approve the completion of units 3 and 4. Chirica was speaking at a London meeting, Nuclear New Build: The Role of the Private Sector, on 27 June.
The Cernavoda plant was originally intended to host five Canadian Candu pressurized heavy water reactors of 633 MWe each. Construction on units 2-5 has halted in 1991 in order to concentrate on unit 1, which entered commercial operation at the end of 1996. It now provides 10% of the country's electricity.
The government decided to resume work on unit 2 in 2000. After some upgrades during completion, unit 2 is rated at 655 MWe.
Negotiations to assemble a commercial consortium for the completion of units 3 and 4 are underway. It is expected that a project company would be formed and work begin in March 2008.
Chirica said the 64 month completion project would cost Eur2.2 billion ($3.0 billion), not including the cost of capital, but would result in two 720 MWe units with 30-40 year lives. He projected the cost of electricity generation by the units would be between Eur28.2-32.5 per MWh ($38.1-43.7).
The units would be constructed in parallel with a gap of "a couple of months" between each unit's start-up around 2014-5.
Further information
Nuclearelectrica
WNA's Nuclear Power in Romania information paper
WNN: Cernavoda 2 achieves initial criticality
Most Read
Czech Republic selects Rolls-Royce SMR for small reactors project
Thursday, 19 September 2024
Study shows existing US sites suitable for new build
Tuesday, 10 September 2024
Construction permit granted for new Korean APR1400 units
Thursday, 12 September 2024
GE Hitachi, Holtec, Rolls-Royce SMR and Westinghouse enter UK SMR negotiations
Thursday, 26 September 2024
Podcasts & Features
Podcast: Financiers back idea of nuclear expansion, but what are the challenges?
Podcasts & Features Tuesday, 24 September 2024
Viewpoint: Building the industrial foundations for new nuclear growth
Podcasts & Features Friday, 20 September 2024