Vendors adapt to financing role

Monday, 15 September 2014
Jerry Hopwood - Candu Energy WNA Sympo 2014 - 48Nuclear power reactor vendors have been forced to adapt to the fact that governments are no longer willing to assume the risks associated with nuclear new build projects, Jerry Hopwood, vice president of product development at Candu Energy, said on 12 September.

Nuclear power reactor vendors have been forced to adapt to the fact that governments are no longer willing to assume the financial risks associated with nuclear new build projects, Jerry Hopwood, vice president of product development at Candu Energy, said on 12 September.

Jerry Hopwood - Candu Energy WNA Sympo 2014 - 460
Candu Energy's Jerry Hopwood speaking at the WNA Symposium (Image: WNA)

"The best way to explain how a vendor like our company Candu Energy approaches financing is we are right at the end of the rope. When people are trying to prepare a project and the project is assembling itself, and time goes forward and time goes back, it's like the rope is wiggling and we’re the guys who get the most wiggle at the end of the rope," Hopwood said at the World Nuclear Association's 2014 Symposium in London. 

"Public-private partnership seems to be where the sector is going."

Jerry Hopwood
Candu Energy

"The vendor is the organization that is most affected by financing because in the end the project either will go or not go and we'll have invested a lot of time and effort of our own in something where there's always uncertainty until financing comes along. And a project can make tremendous economic sense, it can be the right strategic fit, it can be the perfect match between the utility and the vendor, but if there's no financing, there’s no project."

Many jurisdictions have re-evaluated the state-owned model to project cost overruns and schedule delays, high government debt loads, other funding priorities leading to privatization of non-core assets, and technological maturity, he said.

Private sector models are difficult to execute for nuclear projects due to first-of-a-kind issues, their large capital requirement, long construction timescales and investor return expectations. But they can work within a positive framework of incentives – for example the UK's contract for difference model, he said.

Several emerging markets are still developing state-owned models, but are incorporating mechanisms where risks are placed with the appropriate parties, such as nuclear initial public offerings and build-own-operate-transfer.

"Public-private partnership seems to be where the sector is going," he said.

Public-private partnerships


This combination means a project is financed by both the government and a private investor, with the public share able to attract export credit. Such a model requires a power purchase agreement matched to debt obligations and the project risks are allocated between government agencies and private companies.

Regulatory and technology risks are "two separate sides to the same coin," he said. Other risks include engineering, supply and project management; technical services; skilled labour and availability and rates; training and commissioning, and lifetime operational support.

Government sponsored financial incentives encourage private sector companies to take increased financial responsibility for nuclear new build projects.

These include contracts for difference and power purchase agreements, loan guarantees, export credits, carbon credits, and cost and schedule overruns.

"Vendors play a critical role in the success of the public-private partnership model by focusing on key areas, which are project risk reduction and regulatory feedback. No matter how the risks are allocated, if they are too high, you won't get the financing," he said.

For example, licence applications are costly, but it is money well spent as any issues ironed out with the regulator early on will reduce project costs later, he said.

Collaboration


"Working closely with regulators, vendors can ensure that reactor designs meet safety and environmental standards before project deployment," he said. "A vendor pre-project design review of a new nuclear power plant allows the regulatory body an opportunity to assess a design prior to any licensing activities and to identify potential issues that would require resolution."

Further co-ordination between regulators, either bilaterally or through multi-lateral forums, such as MDEP [Multinational Design Evaluation Program], can help to harmonize views and mitigate risks. In that way a design qualified in the home country can be used elsewhere. We need regulatory cooperation across the world," he said.

The success of future new build projects is "imperative" to ensure the long-term sustainability and growth of the industry, he said. "Failure is not an option."

Vendors play a key role, he said, to ensure this success and must work collaboratively with the key stakeholders in a project. Vendors "have to have a certain level of openness" to ensure the success of nuclear power plant projects wherever they are, he said.

Vendor-led financing is not sustainable in the long term, Hopwood said.

"I think it's a sort of kick starting mechanism, a way to get projects going so that we start to have a track record," he told World Nuclear News. "Whether it be in a big way or a small way, it's showing vendor commitment and it's getting some projects on the books and going and creating a track record and that's the value of it and necessarily it must lead to more."

"If we picture a world with many nuclear projects going ahead - there are 71 nuclear units under construction at the moment - the financing requirement is far more than any vendor or even any individual utility can finance, so financing has to come from aggregating from many sectors in order to have a flourishing nuclear industry. The demand for money is going to be so great that it will necessarily require us to seek out all sorts of funding, all kinds of capital formations," he said.