Under the current Reactor Regulation Law, all Japanese nuclear power plants are operated on a 13-month schedule, at the end of which maintenance and safety inspection takes place. However, in other countries is it common for similar reactors to operate on 18-month, or 24-month cycles, providing more consistency for grid managers and better economy for plant owners. The longest uninterrupted run of a light-water reactor is 739 days, recorded at LaSalle 1 in the USA in February.
Now, the Nuclear and Industrial Safety Agency (NISA) has said it will draft a ministerial ordnance with the aim of changing the law. Atoms in Japan reported that the decision was made after discussion with the Japan Power Engineering and Inspection Corporation and the Japan Society of Mechanical Engineers.
Providing ministerial approval is forthcoming, plant owners could apply to extend their operating cycles from the next financial year, which starts in April 2008. In total, three new inspection intervals would be available - at 13, 18 and 24 months, with 13 remaining standard initially.
To change from the default interval of 13 months, plant owners would have to provide extensive evidence of how each item of plant equipment would fare over longer periods, and describe in detail their new maintenance programs and operational plans.
NISA's proposal would be made available for public comment by the end of September and a trial of the new system would be carried out by the end of the year.
Further information
Nuclear Industrial and Safety Agency
WNA's Nuclear Power in Japan information paper
WNN: LaSalle plant runs up another record
Japanese nuclear power plants could begin to operate for up to 24 months between inspections, under changes proposed by industry and safety authorities. The current limit is 13 months.
Japanese nuclear power plants could begin to operate for up to 24 months between inspections, under changes proposed by industry and safety authorities.Under the current Reactor Regulation Law, all Japanese nuclear power plants are operated on a 13-month schedule, at the end of which maintenance and safety inspection takes place. However, in other countries is it common for similar reactors to operate on 18-month, or 24-month cycles, providing more consistency for grid managers and better economy for plant owners. The longest uninterrupted run of a light-water reactor is 739 days, recorded at LaSalle 1 in the USA in February.
Now, the Nuclear and Industrial Safety Agency (NISA) has said it will draft a ministerial ordnance with the aim of changing the law. Atoms in Japan reported that the decision was made after discussion with the Japan Power Engineering and Inspection Corporation and the Japan Society of Mechanical Engineers.
Providing ministerial approval is forthcoming, plant owners could apply to extend their operating cycles from the next financial year, which starts in April 2008. In total, three new inspection intervals would be available - at 13, 18 and 24 months, with 13 remaining standard initially.
To change from the default interval of 13 months, plant owners would have to provide extensive evidence of how each item of plant equipment would fare over longer periods, and describe in detail their new maintenance programs and operational plans.
NISA's proposal would be made available for public comment by the end of September and a trial of the new system would be carried out by the end of the year.
Further information
Nuclear Industrial and Safety Agency
WNA's Nuclear Power in Japan information paper
WNN: LaSalle plant runs up another record
Most Read
Fukushima Daiichi: How is the decommissioning process going to work?
Friday, 4 October 2024
President Biden signs ADVANCE Act into law
Wednesday, 10 July 2024
Guidelines drawn up for AI use in nuclear sector
Thursday, 12 September 2024
ABS sets requirements for floating nuclear power plants
Friday, 4 October 2024
Podcasts & Features
Podcast: What next for UK's record-setting Heysham 2 nuclear power plant?
Podcasts & Features Monday, 11 November 2024
Podcast: The global tech giants choosing nuclear
Podcasts & Features Wednesday, 23 October 2024