Georgia Power has taken delivery of nuclear fuel for Vogtle unit 3. Construction of the AP1000 - one of two being built at the site near Waynesboro - is now about 96% complete. Fuel loading is expected in April, the company said.
Before the fuel could be received, critical infrastructure, including Vogtle 3's fuel vault and used fuel pool, had to be completed and inspected to ensure they met construction quality and design requirements. The fuel handling area has now been passed from site construction to operations, and specific and comprehensive policies, procedures and security measures have been implemented to safely receive, handle and store the nuclear fuel, the company said.
The focus now moves to hot functional testing of unit 3. Cold functional tests were completed in October.
Construction of Vogtle unit 3 began in March 2013 and unit 4 in November the same year. Unit 3 is expected to be in service by November 2021 and unit 4 by November 2022.
Most Read
Study shows existing US sites suitable for new build
Tuesday, 10 September 2024
Construction permit granted for new Korean APR1400 units
Thursday, 12 September 2024
Czech Republic selects Rolls-Royce SMR for small reactors project
Thursday, 19 September 2024
Finnish energy firm Helen launches nuclear programme
Monday, 9 September 2024
Podcasts & Features
Viewpoint: Building the industrial foundations for new nuclear growth
Podcasts & Features Friday, 20 September 2024
Viewpoint: The key takeaways from World Nuclear Symposium
Podcasts & Features Friday, 13 September 2024
Related Information
Related Topics
Related Links