AtomStroyExport unveils schedule for China projects
Alexey Bannik, vice president of China projects at Russia's AtomStroyExport (ASE), has given the schedule for new VVER-1200 units at Tianwan and Xudabao. Construction of Tianwan unit 7 will start in May 2021, and that of Xudabao unit 3 and of Tianwan unit 8 will start five and 10 months later, respectively. The launch of the Tianwan units is scheduled for 2026 and 2027 while the third and fourth units at the Xudabao plant will both be launched in 2028.